Norwalk High School
Gerber Construction is the site and utility contractor for the new Norwalk High School in Norwalk, Connecticut. We moved more than 100,000 cubic yards and installed about four miles of storm, sanitary and water pipe.
City of Norwalk · Norwalk, CT · 2024–present · Mass excavation and grading, storm/sanitary/water utilities, deep structures and underdrain, retaining walls, athletic fields; curbing, sidewalks and paving carried in our contract

Norwalk's new high school campus sits on a tight urban site with a lot of contractors working at once. Gerber's crews excavated, graded and balanced more than 100,000 cubic yards of material to build the building pads, the parking lots and the athletic fields.
Below grade, we installed more than 21,000 linear feet of storm, sanitary and water pipe, including deep storm drainage structures and extensive underdrain systems. Above it, our contract carried the retaining walls, curbing, sidewalks and asphalt paving for both the main campus and the athletic complex.
The job ran on a phased schedule that had to hold for everyone else on site.
Gerber's scope
- Mass excavation and grading
- Storm, sanitary and water utilities
- Deep storm structures and underdrain
- Retaining walls
- Curbing and sidewalks
- Asphalt paving
- Athletic field construction